Determination of the relationship and impact of overtime on the health and performance of construction workers
Keywords:
Construction, Occupational health, Overtime, Worker performance.Abstract
The main objective of this study was to determine the impact of overtime worked in construction processes on the health of the workers and their level of performance, for which it was necessary to determine how the extended working day strategy could improve the management of time and work on site. After carrying out the review of the theoretical bases with which it was possible to establish the state of art, which defined both the research background and the theoretical framework, a representative sample of construction professionals was interviewed to establish their perspective. regarding this situation. The results of the application of the questionnaire were analyzed through descriptive statistics, correlation between questions and factor analysis, which gave the opportunity to establish pertinent inferences and conclusions. With the theoretical and statistical information, a decision diagram was designed to guide the construction site if overtime it to be included as a viable strategy that seeks to improve the management of the site. The results found allowed to define that the extension of the working day, if it is considered prior to the start of the work, should not have a negative impact on the health of the personnel, nor on the work performance, and it is even established that the utility in the building process suffers a marginal loss, and that on the other hand, the decrease in construction times, allows to eliminate the consequences such as the impact of indirect or the possibility of increases or fines for delays, which may have the appearance of unforeseen events in the original of time, for the development of the process. As a main conclusion, it is pointed out that if overtime is carried out, it must be previously considered and never as a last-minute solution. In this sense it will provide positive aspects for both the owner and the builder, but analyzed and accepted in consensus by both, so it should not generate problems for the health or performance of the staff.
References
[1] Eshofonie, F. P. (2008). Factors Affecting Cost of Construction in Nigeria. Covenant University, Trabajo de Grado. Nigeria. Recuperado de: http://eprints.covenantuniversity.edu.ng/346/1/PAT_MSc_1.pdf.
[2] Cho, K.; Hong, T.; Hyun, C. (2010). Integrated Schedule and Cost Model for Repetitive Construction Process. Journal of Management in Engineering. ISSN 0742-597X, (2), 78-88. Corea del Sur. Recuperado de: https://ascelibrary.org/doi/abs/10.1061/%28ASCE%29ME.1943-5479.0000009.
[3] Fernely Moquete, F.; Rodríguez, T. (2015). Evaluación de la Productividad con Jornada de 4/10 en Proyectos de Construcción en Santo Domingo, República Dominicana. Revista Ciencia y Sociedad. ISSN 0378-7680, (1), 171-189. República Dominicana. Recuperado de: https://www.redalyc.org/pdf/870/87038991008.pdf.
[4] Visser, A. (2017). How to Manage Overtime. Finweek. ISSN 1812-4658, 44-45. Sudáfrica. Recuperado de: https://www.news24.com/Fin24/how-to-manage-overtime-20171102.
[5] Watanabe, M.; Yamauchi, K. (2016). Psychosocial Factors of Overtime Work in Relation to Work-Nonwork Balance: A Multilevel Structural Equation Modeling Analysis of Nurses Working in Hospitals. International Journal of Behavioral Medicine. ISSN 1070-5503, (4), 492-500. Japón, DOI: 10.1007/s12529-016-9563-x. Recuperado de: https://pubmed.ncbi.nlm.nih.gov/27102432/.
[6] Näswall, K.; Burt, C.; Pearce, M. (2015). The Moderating Effect of Control over Work Scheduling and Overtime on the Relationship between Workload Demands and Perceived Job Risk. Work Journal. ISSN 1051-9815, (3), 571-577. Nueva Zelanda. DOI: 10.3233/WOR-141885. Recuperado de: https://pubmed.ncbi.nlm.nih.gov/24939119/.
[7] Globerson, S. (2017). Using the Earned Value Approach for Controlling Overhead Cost in Construction Projects. Journal of Modern Project Management. ISSN 2317-3963, 50-55. Israel. Recuperado de: https://journalmodernpm.com/index.php/jmpm/article/view/JMPM01406.
[8] Zaho, L.; Mbachu, J.; Domingo, L. (2017). Exploratory Factors Influencing Building Development Costs in New Zealand. Buildings. ISSN 2075-5309, (3), 1-16. Nueva Zelanda. DOI: 10.3390/buildings7030057. Recuperado de: https://www.researchgate.net/publication/318599284_Exploratory_Factors_Influencing_Building_Development_Costs_in_New_Zealand.
[9] Bhutto, R. (2015). Extended Work Overtime: Labors’ (Employees) Choice or Obligation. South Asian Journal of Management Sciences. ISSN 2074-2967, (2), 63-68. Pakistán. Recuperado de: http://sajms.iurc.edu.pk/issues/2015b/Fall2015V9N2P4.pdf.
[10] Evans, P. (2016). Building Industry Braces for Changes. Grand Rapids Business Journal. ISSN 1045-4055, (26), 3-7. Estados Unidos. Recuperado de: https://grbj.com/news/building-industry-braces-for-changes/.
[11] Pérez Gómez Martínez, G. J. F.; Betancourt Chávez, J. R.; López Montelongo, A. M.; Ponce Palafox, C.; Prince Ríos, J. G. (2017). Revisión de los Factores de Impacto en el Precio de Venta de la Vivienda de Nivel Social. Revista de Arquitectura e Ingeniería. ISSN 1990-8830, (2), 1-13. Cuba. Recuperado de: https://www.redalyc.org/articulo.oa?id=193954081003.
[12] Pérez Gómez Martínez, G. J. F.; Botero Botero, L. F.; Cortés Martínez, F.; Prince Ríos, J. G. (2017). Impact on the Health of the Workforce for the Work in Extras Hours in the Construction. International Journal of Engineering and Technical Research. ISSN 2321-0869, (12), 4-7. India. Recuperado de: https://www.neliti.com/id/publications/264922/impact-on-the-health-of-the-workforce-for-the-work-in-extras-hours-in-the-constr.
[13] Vela Moreno, V. B. (2019). Estudio de las Horas Extraordinarias en la Mano de Obra de la Construcción de la Comarca Lagunera de México. Tesis de Maestría. México. Recuperado de: https://drive.google.com/file/d/1DE6Sfc_hAArZ5Ixp5LPoMTREDrnhwBal/view?usp=sharing.
[14] Narayan, B. (2014). Construction Sector Management: Status of Construction Workers in Mumbai. Journal Research Horizons. ISSN 2229-385X, (4), 86-94. India. Recuperado de: https://mnwc.edu.in/researchhorizon/wp-content/uploads/2020/10/RH-2014.pdf.
[15] González, Y. L. (2015). Evaluación de la percepción del riesgo ocupacional en trabajadores de una empresa del sector de la construcción en Bogotá D.C. NOVA: Publicación Científica en Ciencias Biomédicas, volumen 13, tema 23, pp. 93-107. ISSN 1794-2470. Colombia. Recuperado de: http://www.scielo.org.co/pdf/nova/v13n23/v13n23a09.pdf.
[16] Zahoor, H.; Chan, A. P. C.; Arain, F.; Gao, R.; Utama, W. P. (2016). An Analytical Review of Occupational Safety Research in Pakistan Construction Industry. International Journal of Construction Project Management, volumen 8, tema 2, pp. 125-140, ISSN 1944-1436. Pakistán. Recuperado de: https://www.researchgate.net/publication/311545331_An_Analytical_Review_of_Occupational_Safety_Research_in_Pakistan_Construction_Industry.
[17] Carpio de los Pinos, A. J.; González García, M. N.; Moreu de la Vega, C; Hosokawa Menéndez, K. (2017). Idoneidad y Discrepancia de Métodos de Evaluación de Riesgos en Seguridad y Salud Aplicados en Obras de Construcción. DYNA, Ingeniería e Industria. ISSN 0012-7361, (2), 214-219. España. DOI: https://doi.org/10.6036/8201 Recuperado de: https://www.revistadyna.com/busqueda/idoneidad-y-discrepancia-de-metodos-de-evaluacion-de-riesgos-en-seguridad-y-salud-aplicados-en-obras.
[18] Karimi, H.; Taylor, T. R. B.; Goodrum, P. M. (2017). Analysis of the impact of craft labour availability on North American construction project productivity and schedule performance. Construction Management & Economics, volumen 35, tema 6, pp. 368-380, ISSN 0144-6193. Estados Unidos. DOI: 10.1080/01446193.2017.1294257. Recuperado de: https://www.researchgate.net/publication/316494107_Analysis_of_the_impact_of_craft_labour_availability_on_North_American_construction_project_productivity_and_schedule_performance.
[19] Villarreal, J. A.; Puebla Rodríguez, M.; Fonseca González, R.; Álvarez Rivero, E. B. (2017). La tríada salud-trabajo-ambiente y su impacto en los trabajadores. Revista Salud de los Trabajadores, volumen 25, número 2, páginas 147-155, ISSN 1315-0138. Cuba. Recuperado de: https://www.redalyc.org/pdf/3758/375855579005.pdf.
[20] Dixit, S.; Mandal, S. N.; Sawhney, A.; Singh, S. (2017). Relationship Between Skill Development and Productivity in Construction Sector: A Literature Review. International Journal of Civil Engineering and Technology, volumen 8, tema 8, pp. 649-665, ISSN 0976-6316. India. Recuperado de: https://www.researchgate.net/publication/319479589_Relationship_between_skill_development_and_productivity_in_construction_sector_A_literature_review.
[21] Long, D.; Arroyo, P. (2018). Language, Moods, and Improving Project Performance. 26th Annual Conference of the International Group for Lean Construction. 18-20 Jul 2018. pp. 495-504. India. DOI: 10.24928/2018/0541. Recuperado de: https://www.researchgate.net/publication/326466558_Language_Moods_and_Improving_Project_Performance.
[22] Prince Ríos, J. G. (2018). Impacto de la Mano de Obra Sobre los Procesos Constructivos de la Vivienda Social, en Torreón, Coahuila. Tesis de Licenciatura. Universidad Autónoma de Coahuila. México. Recuperado de: https://drive.google.com/file/d/1yPUIcfgE7EMB8TSmI4fXBCPt7MUXLEDy/view?usp=sharing
[23] Vrijhoef, R.; Dijkstra, J. T.; Koutamanis, A. (2018). Modelling and Simulating Time Use of Site Workers With 4d BIM. 26th Annual Conference of the International Group for Lean Construction. 18-20 Jul 2018. pp. 155-165. India. DOI: 10.24928/2018/0536. Recuperado de: https://www.researchgate.net/publication/326352799_Modelling_and_Simulating_Time_Use_of_Site_Workers_With_4d_BIM.
[24] Ramírez Franco, A. D. (2018). La Formación Profesional en el Desempeño Laboral de los Trabajadores de la Construcción de la Empresa COSAPI. Tesis de Maestría, Universidad Inca Garcilaso de la Vega. Perú. Recuperado de: http://repositorio.uigv.edu.pe/bitstream/handle/20.500.11818/3665/TESIS_MBA_ANASTACIO%20DARDO%20RAMIREZ%20FRANCO.pdf?sequence=2&isAllowed=y.
[25] Sifuentes Valadez, A. A. (2019). Entrevista Personal. Maestro en Arquitectura. México.
[26] Rodarte Ortega, J. J. (2019) Entrevista Personal. Ingeniero Civil. México.
[27] Pérez Gómez Martínez, G. J. F. (2021) Análisis del Impacto Económico en una Construcción, con la Implementación de la Jornada Extendida. Tesis de Doctorado, Universidad Juárez del Estado de Durango. México. Recuperado de: https://docs.google.com/document/d/1YjRZ_CfENofBkvQcP_B3yZ2796jMg2AO/edit#heading=h.gjdgxs.